Welspun Enterprises Secures New Order to Design, Build and Operate 2,000 MLD Water Treatment Plant at Bhandup, Mumbai

  • Welspun Enterprises down 20% from top 

  • raising of funds through issuance of 1,90,47,619 warrants carrying options to subscribe equity shares in the ratio of 1 (One) equity share having face value of Rs. 10/- each at an issue price of Rs. 525/- (Rupees Five Hundred and Twenty-Five Only) (including premium of Rs. 515/-) for 1 (One) warrant, aggregating up to Rs. 1,000 Crore (Rupees One Thousand Crore Only), by way of preferential issue on private placement basis to the proposed Allottees as per Annexure-I in one or more tranches, subject to the approval of the members of the Company, and such other statutory and regulatory approvals as may be applicable
  • Warrants carrying option to subscribe to Equity share in the ratio of 1 (One) equity share having face value of Rs. 10 each at an issue price of Rs. 525/- (Rupees Five Hundred and Twenty-Five Only) (including premium of Rs. 515/-) for 1 (One) warrant, aggregating up to Rs. 1,000 Crore (Rupees One Thousand Crore Only) within 18 months from the date of allotment of warrants in terms of the provisions of the SEBI (Issue of Capital and Disclosure Requirements) Regulations, 2018, and other applicable laws and subject to the approval of the members and other necessary regulatory, statutory and other approvals, permissions and sanctions, as may be applicable

  • Welspun Enterprises Secures New Order to Design, Build and Operate 2,000 MLD Water Treatment Plant at Bhandup, Mumbai

     https://youtu.be/SEfEm9T5WZs?si=jZh2c3-k6VTSphrZ

    • Welspun Enterprises down 20% from top 
    • Welspun Enterprises Secures New Order to Design, Build and Operate 2,000 MLD Water Treatment Plant at Bhandup, Mumbai  
    • Contract value of the plant is Rs. 4,123.88 Crores (including O&M value Rs. 1,880.44 Crores)  
    • The facility will be one of the largest in the world in terms of capacity and will deploy best‐in‐class technologies for sustainable operations 
    • The project is slated to be completed within a timeframe of 48 months, following which WEL will undertake O&M responsibilities for a period of 15 years.  


     Thank you for contacting Rounaq! Please let us know how we can help you. 

    Whatsapp: 7838491131

    SEBI registered RA : Rounaq Bakshi
    Waheguru

    Comments

    Popular posts from this blog

    Transcript of NMDC Limited post Q4 & FY 2024-25 Results

    Looking to park some excess funds for the short term.?

    𝐖𝐑𝐲 𝐃𝐨 ππ‘πˆπ¬ 𝐈𝐧𝐯𝐞𝐬𝐭 𝐒𝐧 𝐈𝐧𝐝𝐒𝐚?